Home > Latest > Body

Yuanxing Energy: The production line of the Alxa Tamusu natural alkali development and utilization project is running under load due to equipment failure

clock
2024-09-05 19:41:40
Gold Ten Futures, September 5th, Yuanxing Energy announced on the evening of September 5th that it recently received a notice from its holding subsidiary, Yingen Mining, that some of the shared equipment in the evaporation link of the third and fourth production lines of the Alxa Tamarin trona development and utilization project failed during operation, causing the two production lines to reduce load and operate, which is expected to affect the output of soda ash by about 3,000 tons/day. Yingen Mining has started emergency repair work and is expected to resume before the end of October 2024.